Separate an automatic demand from a pump that has actually run
Follow tank level, the demand bit, the pump command and the running feedback as four separate observations. Start the pump journey with a low-level condition and note the chosen mode. A simulated level is an input to the sequence, not evidence that a pump has delivered water.
Try the exercise
Select the model's automatic mode and observe the level at which demand changes. Compare the command with the feedback indicator. Repeat with a missing permissive. Record the first bit that differs from the healthy sequence rather than changing the start and stop thresholds together.
Common fault or interpretation error
Confusing high-level stop with low-level start gives a sequence that looks reversed. Write each condition in words before editing the ladder.
Use the observation sheet twice with the same tank level, once in hand and once in automatic mode. Mark where the selected source changes the command chain.
Frequently asked question
Why does a demand bit stay on with the motor stopped?
Demand expresses a process need. An interlock, selector or unavailable output can prevent that request from becoming a motor command. Feedback is an independent clue about the result.
A simple practice routine
- Identify the supply, the load and the control devices before changing the example. Read the terminal names and compare them with the linked guide.
- Make one change, then observe the effect. For a circuit, use the diagram and connection check; for a calculator, check the units and the formula.
- Return the example to its original condition and repeat the task. Save or export a project from its Project menu before leaving if you need a permanent copy.
Understand the example
A PLC repeats the same cycle many times a second: it reads all inputs into memory, solves the program rung by rung from top to bottom, then writes the results to the outputs. Because outputs are written at the end, the order of rungs matters when one rung uses a result from another.
A normally-open contact (XIC, drawn ] [) passes "power" when its bit is 1. A normally-closed contact (XIO, ]/[) passes power when its bit is 0. Contacts in series make an AND; parallel branches make an OR. The output coil (OTE) at the end of the rung sets its bit to the result of the rung on every scan.
Note that the PLC contact type has nothing to do with the field wiring: an emergency stop is wired normally-closed so that a broken wire stops the machine, and the program then checks that its input is ON (XIC) to allow running.
A latch (OTL) sets a bit and keeps it set until an unlatch (OTU) clears it. The pump example latches a "demand" bit when the level falls below the start set-point and unlatches it at the stop set-point, which creates hysteresis.
An on-delay timer (TON) starts timing when its rung becomes true and sets its done bit after the preset time. The example uses one to supervise the pump: if the run command is on but no running feedback arrives within 3 s, the pump is declared failed. A counter (CTU) counts rising edges, such as pump starts.
Comment every rung, use meaningful tag names, keep safety functions (emergency stop, overfill) in hard-wired circuits as well as in the program, and test each rung by forcing its inputs in simulation before commissioning.
Open PLC & Process → Ladder program. Watch the power flow in each rung while the tank fills and empties, and edit a rung to see the effect immediately.
Continue learning
Learning model: follow equipment instructions and applicable local rules for real installations. A simulated check is not installation approval.